|
PUMP STATION
|
|
December 2007
|
.JPG) Driving the sheet piling for the raw sewage pump station (RSPS)
|
|
 Driving sheet piling for the pump station
|
|
 Sheet piling in place for pump station
|
|
February 2008
|
 Pre-excavation for pump station
|
|
 Ramp for equipment to get into pump station site for excation
|
|
 Shot of Pre-excavation activities
|
 Forming the compression ring for concrete pouring
|
|
 Pumper truck used to fill the compression ring
|
|
 Compression ring concrete pour
|
 Covering concrete pour
|
|
|
|
|
|
April 2008
|
 First concrete pour complete in pump station
|
|
 Earth ramp for excavator
|
|
 Misc. debris found during excation
|
 Boulders being excavated from site for pump station
|
|
 Dewatering during excavation
|
|
 Excavation continued
|
 Rebar being brought into excavation site
|
|
|
|
|
|
June 2008
|
 All concrete rings in place for pump station - final depth is 50 feet
|
|
 Concrete bucket being lowered into excavation site
|
|
 Excavating center trench for wet well channel
|
 Center trench for wetwell and formwork for base slab
|
|
 Rebar layed over center trench
|
|
 Lifting D4 Dozer out
|
 Beginning of rebar and formwork for pump station
|
|
|
|
|
|
August 2008
|
, Dry well foundation (2).jpg) Intake Pipe Sleves (1), Dry well foundation (2)
|
|
 Continue to build pump station building, facing the north wall
|
|
 Pump Station construction
|
 Wetwell chamber on left
|
|
 Utility Trench around Pump Station
|
|
|
|
October 2008
|
 Pump Station construction
|
|
 Pumper truck lowered for concrete pour
|
|
 Rebar for Pump Station construction
|
 Wetwell construction
|
|
 Waterproofing the wall of the pump station
|
|
|
|
December 2008
|
 Pouring concrete into forms for Pump Station construction
|
|
.jpg) Influent Chamber (sewer lines enter wetwell)
|
|
, Well Point for dewatering (2), Manhole (3).jpg) Odor Control Pipe (1), Well Point for dewatering (2), Manhole (3)
|
|
February 2009
|
 Cutting sheet piling off below grade
|
|
 Influent chamber, manhole, well point, and odor control pipe area back filled
|
|
 Pump Station construction
|
 Flow meter being installed
|
|
 Lowering the prefabricated stairs into place
|
|
 Raw sewage pumps before installation
|
 Bar screen
|
|
 Bar screen being lifted
|
|
|
|
April 2009
|
 Steel frame of pump station building being installed
|
|
 Frame construction
|
|
 Pump station building
|
 Exhaust ductwork inside the Pumping Station
|
|
 Pumps for hydraulic gates before installation
|
|
 Bases in place for Raw Sewage Pumps
|
 Raw Sewage Pump in place
|
|
 Serpentine conveyor
|
|
 Suction lines being installed
|
|
GRIT BUILDING
|
 Basement of Grit Building
|
|
 Grit Cell Concentrators
|
|
 Grit Cell being constructed
|
 Grit concentrators being offloaded and installed
|
|
 Grit Building during construction
|
|
.jpg) Grit building during construction (2)
|
 Electrical equipment in basement
|
|
 Grit snail - conveyor
|
|
.jpg) Grit pump (1 of 3)
|
 Grit channel
|
|
|
|
|
|
BLOWER BUILDING
|
 Blower Building Excavation - Looking NE
|
|
 Pile cap blankets at site of new Blower Building
|
|
 Pile caps at site of new Blower Building
|
 Temporary airline at aeration tank next to site of new Blower Building
|
|
 Blower Building partway through construction; Aeration tank in front
|
|
 Cable Tray carrying cables to Blower Building
|
 Air line leaving Blower Building
|
|
 Blower Building roof fans before installation
|
|
 Roof of Blower Building
|
 Blower Building - installed roof fans
|
|
 Blower Building discharge piping
|
|
 Blower Building Electrical Room during construction
|
|
NON-POTABLE BUILDING
|
 Non-Potable building during construction
|
|
 Non-Potable building during construction
|
|
 Roof of Non-Potable building
|
 Non-potable pumps
|
|
 Strainer in Non-Potable building
|
|
|
|
ELECTRICAL SUBSTATION/EMERGENCY GENERATORS
|
 Electrical Substation Pre-Fabricated building being delivered
|
|
 Electrical Substation before final placement
|
|
 Preparing Electrical Substation for lift and placement
|
 Electrical Substation being lifted up in air
|
|
 Moving Electrical Substation for final placement
|
|
 Moving Electrical Substation
|
 Electrical Substation set into place
|
|
 Electrical Substation Left, Emergency Generator Building Right
|
|
 Interior view of Electrical Substation
|
 Electrical Substation vault cable entrance
|
|
 Sub-base for the transformer pads, next to Electrical Substation
|
|
 One one two Emergency Generators
|
|
TEMPORARY BYPASS DURING CONSTRUCTION
|
 Bypass piping being installed
|
|
 One of twelve Pumps for use during construction
|
|
 Bypass pipes during construction
|
 Bypass pipes during construction
|
|
 Temp orary bridge for bypass pumps
|
|
 Temporary Bypass piping
|
|
GENERAL MSANK SITE PHOTOS
|
 Old pipe removed for replacement
|
|
 Old Raw Sewage Pipe
|
|
 Four foot diameter drill bit
|
 Core drilled using four foot drill bit
|
|
 Concrete pourer
|
|
 Tinted concrete poured over utility lines
|
 Metal railings for use around site, before unwrapping
|
|
 Screen shot of SCADA system used for whole MSANK site
|
|
|